Coal Ministry Denies Coal Shortage Behind Punjab Power Crisis
Coal Ministry rejects coal supply shortage as the cause of Punjab's power crisis, citing low plant utilisation, IPP breakdowns and adequate coal stocks.
Key Highlights:
- The Coal Ministry denied that inadequate coal supply caused Punjab's reduced power generation.
- It attributed the crisis to low utilisation of PSPCL's own plants, IPP breakdowns and delayed coal lifting.
- Coal from PSPCL's Pachhwara mine has been enabled for supply to independent power plants, including Nabha Power and Talwandi Sabo Power.
- Rake supply to both Nabha Power and Talwandi Sabo Power has exceeded their average consumption in recent days.
- As of September 11, coal stock at PSPCL's plants stood at around 114% of the normative requirement.
Ministry Pushes Back on Coal Shortage Narrative
The Ministry of Coal on Sunday clarified that adequate coal has been made available to power plants in Punjab, directly rejecting media reports that had attributed the state's reduced power generation to inadequate coal supply. Instead, the ministry pointed to a combination of factors, including low utilisation of Punjab's own power plants, reported breakdowns at independent power plants, and delayed lifting of coal already offered by Coal India Limited.
Responding Directly to Media Reports
The clarification came specifically in response to media coverage that had linked reduced generation at Punjab's thermal plants to plant outages and coal supply shortfalls. By issuing a detailed rebuttal, the ministry appears to be aiming to shift the narrative around Punjab's power generation issues away from a supply-side problem and toward operational and logistical factors within the state's own power infrastructure.
Steps Already Taken to Enable Coal Movement
According to the ministry, the government has already enabled coal movement to Punjab's independent power plants from PSPCL's captive mines, with Coal India Limited reiterating its commitment to ensuring uninterrupted coal supply for power generation in the state. The ministry said that higher utilisation of PSPCL's own plants, closer monitoring of breakdowns at independent power plants, and timely lifting of coal already offered by CIL subsidiaries would together help optimise power generation and meet Punjab's requirements going forward.